2026 Pavement Management Program – Mill and Overlay List of Streets and Schedule Updates
Please note that the schedule is weather dependent and subject to change
- S 17th Street (Shawnee to Cherokee)-Completed
- Sanders Street (Grand Ave. to Dead End)-Delayed
- S 10th Avenue (Gatewood to 180’ south of Limit)-Wed, August 12th, 2026 (Milling), Thurs, August 13th, 2026 (Paving)
- 4th Street (Spruce to Custer)-Mon, August 10th, 2026 (Milling), Tues, August 11th, 2026 (Paving)
- 5th Avenue (Spruce Street to Middle Street)-Fri, August 7th, 2026 (Paving)
- N 22nd Street St (Ottawa Street to ~1150 S of Ottawa Street)-Completed
- Spruce Street (3rdth St. to Esplanade)-Fri, August 14th, 2026 (Milling), Mon, August 17th, 2026 (Paving)
- Congress Street (West 7th Street to 2nd Ave.)-Fri, August 7th, 2026 (Paving)
- Pottawatomie Street (12th Street to 10th Street)-Completed
- Dakota Street (18th Street to 16th Street)-Completed
- Independence Ct (East and West of 14th to Cul de Sac, including Gatewood Ct)-Completed
- Delaware Street (15th Street to 14th Street)-Completed
- N 17th Street (Shawnee Street to Ottawa Street)-Completed
- Parking lot Reconstruction at the Waste Water Treatment Plant (1800 S 2nd Street)-Fri, August 14th, 2026 (Milling), Mon, August 17th, 2026 (Paving)
- Madison Street (Spruce Street to Quincy Street)-Completed
- Grand Avenue (Ohio Street to Halderman Street)-Completed
Contractor: Little Joe's Asphalt
Bid: $1,194,041
Start Date: July 2026